Cost to Demolish a House in NZ: What Auckland Developers Pay Before the Digger Arrives
Quick answer: The cost to demolish a house in NZ is the contractor’s quote plus a stack of fixed charges most budgets miss. In Auckland that means an asbestos survey, Vector’s $795 disconnection, Watercare’s $682.97 meter disconnection and, in a Special Character Area, a resource consent.
Most developers price a demolition the same way. They get a quote from a demolition contractor, add a contingency, and move on to the numbers that feel bigger. Then the programme slips by six weeks before a machine has touched the site.
That happens because the demolition contractor’s price is only one line in the real cost. The rest sits with four other parties: the council, WorkSafe, the network companies and, on older sites, Heritage New Zealand. Each has its own rules, its own fees and its own lead time. None of them works to your settlement date.
Imagine you’ve just bought a 1960s weatherboard house on a 700m² section in Papatoetoe. The plan is to clear it and build three townhouses.
Your finance is drawn, your interest clock is running, and the house has to come down before anything else can happen. What stands between you and a clear site? Swap Papatoetoe for Avondale or Mt Albert and the list is the same. The only thing that changes is whether an overlay applies.
More than most people expect. A house built before 2000 can’t be demolished until someone competent has inspected it for asbestos. The power, gas and water have to be formally disconnected, and the published lead times for those run up to six weeks each. If the site carries a Special Character Areas overlay, the demolition itself can need a resource consent (the council’s formal permission to use land in a particular way). And if the house pre-dates 1900, a separate heritage authority may apply.
This guide works through each of those layers in the order they bite, with the fixed charges we could confirm from the organisations that set them. Where a figure is set by a contractor and varies by site, we say so rather than guess. Design questions for character and heritage homes sit with our architectural partner, and we link to their guidance rather than repeat it.
Do You Need a Consent to Demolish a House in Auckland?
This is the question that trips up more developers than any other part of a demolition. The answer depends on two separate sets of rules, and they give different answers.
The first set is the Building Act 2004, which controls the physical work. The second is the Auckland Unitary Plan (the single planning document that sets zoning and development rules across the whole of Auckland), which controls what you’re allowed to do with the land. A demolition can be exempt under one and still need permission under the other.
The Building Act exemption most people don’t know about
A building consent is the council’s permission for construction work to go ahead. The Building Act counts demolition as building work. Its definition of building work covers work “for, or in connection with, the construction, alteration, demolition, or removal of a building”. So by default, demolition sits inside the consent system.
But Schedule 1 of the Act lists work that doesn’t need a building consent. Clause 30 of Schedule 1 of the Building Act exempts “the complete demolition of a building that is detached and is not more than 3 storeys.”
For a typical Auckland development site, that covers a lot. A detached bungalow, a stand-alone villa, a single-storey brick-and-tile unit on its own: all detached, all under three storeys. If you’re clearing one of those completely, the Building Act doesn’t require a building consent for the demolition.
Two things fall outside the exemption. An attached building isn’t covered, so demolishing one half of a pair of semi-detached units, or a unit in a block of flats, needs a closer look. And partial demolition is handled by a different clause. Clause 31 exempts removing a building element from a building of three storeys or fewer only where the removal doesn’t affect the primary structure, any specified system (such as a sprinkler system) or any fire separation.
The condition that makes the exemption conditional
Here is the part that matters more than the exemption itself. Schedule 1 work only escapes the consent requirement if it meets the conditions in section 42A of the Building Act. One of those conditions is that “the building work does not breach any other enactment.”
Read that as a sequencing rule. If another law or plan requires permission before the house comes down, the Building Act exemption doesn’t help you until that permission is in hand. Two of those other layers are common enough in Auckland to check on every site.
Special Character Areas: where demolition itself needs resource consent
The Unitary Plan’s Special Character Areas Overlay (chapter D18) exists to protect streets whose older housing gives the area its character. Under Table D18.4.1 of the Special Character Areas Overlay, total demolition, or substantial demolition exceeding 30 per cent by area of wall elevations and roof areas, is a restricted discretionary activity. Restricted discretionary means you need a resource consent, and the council can decline it, but only on the matters the plan lists.
The rule also catches removing a building from the site and relocating it within the site, so trucking the house away doesn’t sidestep it. Accessory buildings such as garages are excluded. It applies to every site in the Isthmus A special character area, and to other sites mapped as subject to demolition rules in the overlay statements.
The version of the chapter we checked is dated July 2026 and carries modification markers for Plan Change 120, a council plan change still working through the process. Treat the rule as live, and check whether any Plan Change 120 modification affects your specific site before you commit to a demolition date.
If the property is also in the Historic Heritage Overlay (chapter D17), the demolition rules are stricter again. Sonder Architecture’s guide to Auckland’s heritage overlays covers how D17 and D18 differ and what the consent path involves.
Houses built before 1900: the heritage authority layer
The second layer is national. Under the Heritage New Zealand Pouhere Taonga Act 2014, an archaeological site includes any place, including a building, associated with human activity before 1900 that may provide evidence about New Zealand’s history through archaeological methods.
Section 42 of the Heritage New Zealand Pouhere Taonga Act says no person may modify or destroy an archaeological site without an authority if they know, or ought reasonably to have suspected, that it’s one. Subsection (3) carves out ordinary work on a pre-1900 building, unless the work will result in the demolition of the whole of the building.
So a full demolition of a genuinely pre-1900 house can need an archaeological authority, applied for through Heritage New Zealand, whether or not the house is on any heritage list. The duty doesn’t depend on the site being recorded. If your title, the council records or the building itself point to the nineteenth century, raise it before you sign a demolition contract.
Important: Whether your demolition needs a resource consent, a building consent or a heritage authority is a site-specific call. Confirm the overlay position with Auckland Council or a planner, and the Building Act position with the council’s building consent team, before you set a demolition date. The Building Act text is on legislation.govt.nz.
🏠 Development tip: Check the overlay maps before you go unconditional, not after. A Special Character Areas demolition control changes the feasibility of the whole project, not just the demolition line of the budget.
Not sure whether your site carries a demolition control? It’s one of the first things we check when a developer brings us a site, and you can talk it through with us in a free consultation before you commit.
Asbestos Comes First: The Survey, the Licence Classes and the WorkSafe Notice
If the house was built before the year 2000, asbestos isn’t a maybe. It’s a legal step with its own sequence, and nothing else on site can start until it’s done.
The rules sit in the Health and Safety at Work (Asbestos) Regulations 2016. They apply to anyone running a business or undertaking, which the regulations call a PCBU (a person conducting a business or undertaking). Your demolition contractor is a PCBU. So is your asbestos removalist. As the developer, you’ll usually be the one commissioning both, which makes the sequence your problem even where the legal duty sits with them.
Which houses the rules apply to
Under regulation 19, the demolition rules apply to any structure built or installed before 1 January 2000, or any structure where asbestos has been identified or is likely to be present. For most Auckland infill sites, where the house being cleared dates from the 1950s to the 1980s, that’s every site.
The inspection before the demolition
Regulation 20 sets the order of events. The PCBU planning the demolition “must not carry out the demolition or refurbishment until the structure or plant has been inspected to determine whether asbestos or ACM is fixed to or installed in” it. ACM means asbestos-containing material. The inspection has to be done by a competent person.
Two further details are worth knowing. If the competent person is uncertain, or part of the house is inaccessible and likely to be disturbed, the regulations require the PCBU to assume asbestos is present. Parts of a house that can’t be opened up before demolition, such as wall cavities and sub-floor spaces, can be caught by that rule. And where the workplace is a home, the owner and the occupier must be told if asbestos is found or assumed.
In practice, the inspection is a demolition survey, which is more intrusive than the survey an owner might commission before a small renovation. Because the house is coming down, the surveyor can sample materials that would otherwise be left alone. Ask for a demolition survey by name when you brief the surveyor.
Removal before demolition
Regulation 22 requires a PCBU demolishing a home to ensure that all asbestos likely to be disturbed is identified and, so far as is reasonably practicable, removed before the demolition starts. Breaching it carries a fine of up to $10,000 for an individual and up to $50,000 for any other person, such as a company.
Who can remove it depends on what it’s and how much there is:
| What is being removed | Licence required | Source |
|---|---|---|
| Friable asbestos (in powder form, or able to be crumbled or reduced to powder by hand pressure when dry) | Class A asbestos removal licence | Regulation 54 |
| More than 10m² of non-friable asbestos or ACM, counted cumulatively over the whole removal project for the site | Class B licence (or Class A) | Regulation 56 |
| Written notice to WorkSafe before licensed removal starts | At least 5 days’ notice from the licensed removalist | Regulation 34 |
| Clearance certificate before the removal area is reoccupied | Issued by a licensed asbestos assessor or competent person | Regulation 42 |
That 10m² threshold is smaller than it sounds. It counts the whole project on the site, not each room or each visit, so a house with asbestos-containing cladding, soffits or floor coverings passes it quickly. You can check whether a removalist holds a current licence on WorkSafe’s asbestos licence holder register.
What the asbestos step does to your programme
Count the steps: survey, results, removal quote, the five-day WorkSafe notice, the removal itself, then the clearance inspection. Only after that does the demolition contractor get a clean house to take down. None of those steps can overlap with the demolition, because the regulations put removal first.
“On a cleared site the machinery is the quick part. The weeks go on the steps that have to happen in order before anyone is allowed to start it, and asbestos is the first of them.”
— Superior Homes Team
🏠 Development tip: Book the demolition survey during your due diligence period if the vendor will allow access. The result changes your demolition budget, and a sale and purchase agreement is a better place to price that risk than a construction loan.
WorkSafe’s guidance for homeowners is a useful plain-English companion to the regulations if you’re selling or clearing a family property rather than running a development company.
Disconnections: The Part of the Demolition Timeline Nobody Prices
Ask a developer how long a demolition takes and you’ll usually hear about the machine time. Ask the network companies and you get a very different answer.
Before a house can come down, the electricity, gas and water services have to be disconnected by the companies that own them. In Auckland, that means Vector for electricity and for gas on its network, and Watercare (Auckland’s council-owned water and wastewater provider) for water and wastewater. All three publish their process, and all three are clear that you don’t demolish until they say so.
Electricity: Vector’s fee and the written clearance
Vector arranges a permanent electricity disconnection where a customer wants to demolish or relocate a building. According to Vector’s permanent disconnection page, fees apply from 22 April 2026, and the fee depends on how the house is connected.
Once the assessment is done, Vector says the disconnection is usually completed within 5 working days or 4 to 6 weeks, depending on the type of work. The critical instruction is this one: you “must always wait for our written clearance that the electricity services have been safely disconnected before you start to demolish or remove a building.”
Two more points matter for a developer.
Any service cables on your side of the point of supply that Vector doesn’t own remain your responsibility, whether they stay or go. And Vector states that you can’t reuse the old ICP number (the installation control point, the identifier for a property’s electricity connection) when you build a new house. You apply for a new one. A pit or pillar supply point can be reused if capacity is available. An overhead or breach joint supply needs a new one.
Gas: through your retailer, on a longer clock
Gas runs through your gas retailer first. Vector’s gas disconnection page says it aims to quote your retailer within 10 working days and to complete the job within 4 to 6 weeks after the quote is accepted. The work usually involves digging, isolating the service pipe, removing the meter and cutting the riser below ground.
The same written-confirmation rule applies, and it’s precise: wait for confirmation that the gas services, not just the meter, are disconnected before you work near the service or demolish. Any remaining gas pipes on the property are yours.
Water and wastewater: Watercare’s permission and the six-week lead
Watercare’s change a connection page states that you must not disconnect from its networks without its permission, and that both a disconnected water meter and a disconnected wastewater stub must be capped and sealed. It recommends applying at least six weeks ahead of the required work for domestic connections.
For a water meter disconnection, Watercare asks for a plan showing the meter to disconnect and any meters that will remain. For wastewater, it wants a drainage or site plan showing the connection to be disconnected and any that stay. If you’re clearing a site for multiple dwellings, your drainlayer and engineer should be producing those plans already, so ask for them early.
The infrastructure growth charge question to ask before you disconnect
Watercare’s page carries a line every developer should read twice. If you want to reconnect in the future, “you will need to apply for and pay for a new connection, which may include infrastructure growth charges.”
An infrastructure growth charge, or IGC, is Watercare’s contribution towards the bulk network needed for new demand. Watercare’s 2026-2027 schedule sets the Metropolitan charge for water and wastewater at $29,348.46 including GST per residential unit, reduced to two-thirds of the general rate for a unit with a gross floor area of 65m² or less. It applies where a development increases demand, including increasing the number of residential units.
On a one-for-three redevelopment you expect to pay IGC on the additional units. What you want in writing, before you disconnect, is how Watercare will treat the existing connection when the replacement homes connect. The page says reconnection “may” include IGC. That word is worth a written answer.
| Service | Published fee (incl GST) | Published lead time |
|---|---|---|
| Vector electricity, overhead or underground pillar | $795 | 5 working days or 4 to 6 weeks after assessment |
| Vector electricity, underground service pit | $795 | 5 working days or 4 to 6 weeks after assessment |
| Vector electricity, breach joint (a service cable joined straight onto the street cable, with no pillar or pit; fee includes traffic management) | $3,680 | 5 working days or 4 to 6 weeks after assessment |
| Vector gas, via your gas retailer | Quoted per job | Quote within 10 working days; work within 4 to 6 weeks of acceptance |
| Watercare, 15 to 25mm water meter disconnection | $682.97, plus hourly application processing and inspection (one-hour minimum: $230.53 technician, $258.89 engineer) | Apply at least 6 weeks ahead |
| Watercare, wastewater stub disconnection | Confirm with Watercare on application | Apply at least 6 weeks ahead |
Vector fees are from its permanent disconnection page, effective 22 April 2026. Watercare fees are from its 2026-2027 charges schedule, effective 1 July 2026, which states its connection and development charges apply to residential and business customers unless otherwise stated.
🏠 Development tip: Lodge all three disconnection requests on the same day, as soon as settlement is certain. Run one after another, the published lead times can add up to more than three months; run in parallel, the longest one sets your date.
What Goes Into the Cost to Demolish a House in NZ
Now back to the number everyone wants. There’s no honest single figure for the cost to demolish a house in NZ, because the biggest line is a contractor’s price that depends on the house, the site and what the survey finds. What you can do is split the cost into parts you can pin down now and parts you have to price per site.
The cost stack, line by line
| Cost line | Fixed or variable? | What sets it |
|---|---|---|
| Asbestos demolition survey | Variable | House size, number of samples, laboratory testing |
| Licensed asbestos removal and clearance certificate | Variable | What the survey finds, friable or non-friable, total area |
| Electricity disconnection | Fixed (published) | $795 or $3,680 incl GST, depending on the connection type |
| Gas disconnection | Quoted | Vector quote to your gas retailer |
| Water meter disconnection | Fixed (published) plus hourly processing | $682.97 incl GST for a 15 to 25mm meter |
| Resource consent for demolition (Special Character Areas sites only) | Variable | Council deposit and processing charges, planner’s fees, any heritage or character assessment |
| Demolition contractor | Variable | Floor area, construction type, access, foundations to remove, disposal |
| Holding cost while the steps run | Variable | Your loan interest and rates for every week the site isn’t cleared |
We’ve not put a dollar figure against the contractor line. Published “average demolition cost” ranges exist, but none we found was tied to a named, checkable source, and a range that could be out by a factor of three is no help when you’re setting a feasibility. Three written quotes on the same scope will tell you more than any average.
What a demolition quote should spell out
Quotes vary as much in what they include as in their totals. Before you compare prices, make sure every quote answers the same questions:
- Foundations: are piles, slabs and footings removed, and to what depth?
- Driveways, paths and outbuildings: in or out? Garages are often priced separately.
- Trees and vegetation: is clearance included, and has anyone checked whether a tree is protected?
- Disposal: where does the waste go, and is the disposal charge in the price or passed on at cost?
- Salvage: is the contractor crediting you for recoverable timber, bricks or fittings, or keeping them?
- Asbestos: is removal included, excluded, or priced as a provisional sum pending the survey?
- Site finish: what state is the ground left in, and who fills the holes left by old foundations?
That last one matters more than it looks. If the contractor backfills old foundation holes with uncontrolled material, your geotechnical engineer may later treat that part of the site as fill, which can change the foundation design for the new build. Agree the finish level and backfill method in writing, and brief your engineer on it.
Disposal and the waste levy
Disposal is where a demolition price moves most between contractors. Under section 26 of the Waste Minimisation Act 2008, a levy is imposed on waste disposed of at a disposal facility, at a per-tonne rate set by regulation. Every tonne that goes to landfill carries it. Every tonne that’s recovered for reuse or recycling generally doesn’t.
So a contractor with a strong salvage and recycling operation isn’t just greener. They can be cheaper on a heavy house, because less of it’s paying the levy. Ask each contractor what proportion of the building they expect to divert from landfill, and how that shows up in the price.
Demolish or remove?
Some older Auckland houses are worth more on a truck than in a skip. House removal, where a relocation company lifts the house and takes it away whole, can reduce or even offset the demolition cost if the house is in good enough condition to relocate.
The same checks still apply. Asbestos still has to be dealt with if the move will disturb it, the network disconnections are identical, and on a Special Character Areas site the overlay rule covers removal just as it covers demolition. Get a removal company’s assessment early, because if it works, it changes who pays whom.
🏠 Development tip: Put the holding cost in the feasibility as its own line. On a development loan, every week between settlement and a cleared site is interest with nothing to show for it, and the disconnection lead times alone can make that a meaningful number.
How that holding cost interacts with your lender’s drawdown schedule is covered in our guide to development finance in Auckland.
The Pre-Demolition Checklist: One Page, In Order
Everything above collapses into one sequence. The order matters because most steps can’t legally start until the one before is finished.
| Step | Who | What to hold before moving on |
|---|---|---|
| 1. Overlay and heritage check | You, with a planner | Confirmation of any Special Character Areas or heritage overlay, and whether the building could be pre-1900 |
| 2. Consents and authorities | Planner, council, Heritage New Zealand | Resource consent or archaeological authority if required; building consent if the building is attached or over three storeys |
| 3. Disconnection applications | You, your drainlayer, your gas retailer | Applications lodged with Vector and Watercare, and a written answer on how IGC will apply to the replacement homes |
| 4. Asbestos demolition survey | Competent surveyor | Written survey report identifying all asbestos likely to be disturbed |
| 5. Asbestos removal | Licensed removalist | Five-day WorkSafe notice given, removal done, clearance certificate issued |
| 6. Written disconnection clearances | Vector (electricity and gas), Watercare | Written clearance from each network company |
| 7. Demolition and site finish | Demolition contractor | Cleared site at the agreed level, backfill method recorded for your engineer |
Steps 3 and 4 can run side by side, and they should. The disconnection lead times are long enough that lodging them after the asbestos work is finished is the single easiest way to lose a month.
Where this sits in a development we run
On our own projects, demolition isn’t a separate job bolted onto the front of a build. It’s the first stage of the development programme, sequenced against the consent, the finance drawdowns and the build start. You can see how we line up asbestos removal, disconnections and demolition ahead of a build on our development process page.
If you’re still deciding what to build once the site is clear, our guide to townhouse development in Auckland walks through the feasibility side, and our guide to the subdivision consent process covers the application that usually follows.
Keeping the Cost to Demolish a House in NZ Predictable
The cost to demolish a house in NZ is rarely the problem on its own. The problem is the order: a consent that has to exist before an exemption applies, an asbestos survey that has to come before removal, a removal that has to come before demolition, and three network companies that each want written notice and weeks of lead time.
Get the order right and the demolition becomes a predictable line in your feasibility. Get it wrong and it becomes the reason your build starts late. Start the overlay check and the disconnection applications the week your purchase goes unconditional.
➡ Book a free consultation with Superior Homes
➡ See our completed Auckland projects
➡ See the development work we run on Auckland sites, from a cleared section onward
Do I need a building consent to demolish a house in NZ?
Often not. Clause 30 of Schedule 1 of the Building Act 2004 exempts the complete demolition of a building that is detached and not more than three storeys. The exemption only applies if the work meets the conditions in section 42A, including that it does not breach any other enactment. So if the Auckland Unitary Plan requires resource consent for the demolition, or a heritage authority is needed, those must be in place first. Attached buildings and partial demolitions fall outside clause 30 and need to be checked with the council.
What makes up the cost to demolish a house in NZ?
The demolition contractor's quote is only one part. The full cost includes an asbestos demolition survey, any licensed asbestos removal and clearance certificate, network disconnections, disposal of waste, any resource consent needed on a Special Character Areas site, and the holding cost of your loan while those steps run. In Auckland, Vector's published electricity disconnection fee is $795 or $3,680 including GST depending on the connection type, and Watercare's 15 to 25mm water meter disconnection is $682.97 including GST plus processing.
Do I need an asbestos survey before demolishing a house?
Yes, if the house was built before 1 January 2000 or asbestos is known or likely to be present. Regulation 20 of the Health and Safety at Work (Asbestos) Regulations 2016 says the business carrying out the demolition must not start until a competent person has inspected the building for asbestos or asbestos-containing material. Where the inspector is uncertain, or part of the house is inaccessible and likely to be disturbed, the regulations require the business to assume asbestos is present.
Who is allowed to remove asbestos before a demolition?
It depends on the type and amount. Regulation 54 requires a Class A asbestos removal licence to remove friable asbestos, which is material in powder form or able to be crumbled or reduced to powder by hand pressure when dry. Regulation 56 requires a Class B licence, or a Class A licence, to remove more than 10 square metres of non-friable asbestos or asbestos-containing material, counted cumulatively over the whole removal project for the site. WorkSafe publishes a register of current licence holders.
How much notice does WorkSafe need before asbestos removal?
Regulation 34 of the Health and Safety at Work (Asbestos) Regulations 2016 requires a licensed asbestos removalist to give written notice to WorkSafe at least 5 days before starting licensed removal work. The notice must name the removalist, their licence number, the supervisor, the person engaged to carry out the clearance inspection, and the person the work is being done for. Immediate removal without notice is only allowed for sudden, unexpected events such as an equipment failure.
How long does it take to disconnect power, gas and water before demolition in Auckland?
Vector says a permanent electricity disconnection is usually completed within 5 working days or 4 to 6 weeks after its assessment, depending on the work. For gas, Vector aims to quote your gas retailer within 10 working days and complete the job within 4 to 6 weeks of the quote being accepted. Watercare recommends applying at least six weeks ahead of the required work for a domestic connection. Lodging all three at once is the fastest route.
Can I start demolition as soon as the power is off?
No. Vector states that you must wait for its written clearance that the electricity services have been safely disconnected before you start to demolish or remove a building. For gas, it says to wait for written confirmation that the gas services, not just the meter, are disconnected. Watercare states that you must not disconnect from its networks without its permission, and that disconnected water meters and wastewater stubs must be capped and sealed.
Will I pay Watercare's infrastructure growth charge again after demolishing and rebuilding?
Possibly, so ask before you disconnect. Watercare states that if you reconnect in the future you will need to apply for and pay for a new connection, which may include infrastructure growth charges. Its 2026-2027 Metropolitan charge for water and wastewater is $29,348.46 including GST per residential unit, reduced to two-thirds for units of 65 square metres or less. Get Watercare's position on your existing connection in writing before the meter comes out.
Can I demolish a house in a Special Character Area in Auckland?
You can apply, but you will usually need resource consent first. Table D18.4.1 of the Auckland Unitary Plan's Special Character Areas Overlay makes total demolition, or substantial demolition exceeding 30 per cent by area of wall elevations and roof areas, a restricted discretionary activity on sites subject to the demolition rules. That includes all of the Isthmus A special character area. The chapter currently shows proposed Plan Change 120 modifications, so check the position for your site with a planner.
Does a house built before 1900 need a heritage authority to demolish?
It can. The Heritage New Zealand Pouhere Taonga Act 2014 treats a building associated with human activity before 1900 as an archaeological site if it may provide evidence about New Zealand history through archaeological methods. Section 42 says ordinary work on such a building does not need an authority, unless the work will result in the demolition of the whole building. The duty applies whether or not the site is recorded or listed, so check with Heritage New Zealand early.
Is it cheaper to remove a house than demolish it?
It can be, if the house is in good enough condition for a relocation company to lift it and take it away, because the house itself has value. Removal does not avoid the other steps. Asbestos still has to be managed if the move will disturb it, the network disconnections are the same, and on a Special Character Areas site the overlay rule covers removing a building from the site as well as demolishing it. Get a removal assessment before you commit to demolition.
Free Guide: Avoid Costly Mistakes When Building or Developing
Download our free guide — everything you need to know before you build or develop in Auckland, put together by the Superior Homes team.
References
- Building Act 2004, Schedule 1 clause 30 (demolition of detached building) — legislation.govt.nz
- Building Act 2004, section 42A (conditions on Schedule 1 exempt work) — legislation.govt.nz
- Health and Safety at Work (Asbestos) Regulations 2016 — legislation.govt.nz
- Heritage New Zealand Pouhere Taonga Act 2014, section 42 — legislation.govt.nz
- Waste Minimisation Act 2008, section 26 (waste levy) — legislation.govt.nz
- Auckland Unitary Plan, D18 Special Character Areas Overlay – Residential and Business — Auckland Council
- Vector — Permanent electricity disconnection
- Vector — Gas disconnection
- Watercare — Change or relocate a connection
- Watercare — Water services and wastewater charges and IGC 2026-2027
- WorkSafe — Asbestos licence holder register
- WorkSafe — Asbestos information for homeowners
- Heritage New Zealand Pouhere Taonga — Affecting an archaeological site